Contract award
THE BOEING COMPANY
IGF::OT::IGF THE COMMERCIAL CREW PROGRAM (CCP) COMMERCIAL CREW TRANSPORTATION CAPABILITY (CCTCAP) CONTRACT WILL PROVIDE COMPLETION OF THE DESIGN, DEVELOPMENT, TEST, EVALUATION, AND CERTIFICATION OF AN INTEGRATED CREW TRANSPORTATION SYSTEM (CTS) CAPABLE OF TRANSPORTING NASA CREW TO AND FROM THE ISS, IN ACCORDANCE WITH THE DESIGN REFERENCE MISSIONS AND NASA S CERTIFICATION STANDARDS AND REQUIREMENTS. CERTIFICATION OF THE CTS WILL BE DETERMINED BY NASA. NASA PLANS TO ISSUE TASK ORDERS FOR POST CERTIFICATION MISSIONS (PCM) TO AND FROM ISS THAT INCLUDE GROUND, LAUNCH, LIFEBOAT, ON-ORBIT, RETURN AND RECOVERY OPERATIONS. THE MINIMUM QUANTITY OF MISSIONS TO BE ORDERED IS TWO (2) AND THE MAXIMUM POTENTIAL QUANTITY OF MISSIONS WHICH MAY BE ORDERED IS SIX (6). IN ADDITION, NASA MAY ISSUE TASK ORDERS FOR SPECIAL STUDIES USED FOR RISK REDUCTION AND OTHER PURPOSES RELATED TO THE CTS. NASA CERTIFICATION UNDER CLIN 001 IS COMPLETE WHEN THE CONTRACTOR S CREW TRANSPORTATION SYSTEM (CTS) HAS MET NASA S REQUIREMENTS FOR SAFELY TRANSPORTING CREW TO AND FROM THE INTERNATIONAL SPACE STATION (ISS) IN ACCORDANCE WITH DOCUMENTS IDENTIFIED IN SECTION C.1, SPECIFICATIONS/STATEMENT OF WORK. SUBCLINS 001A AND 001B, IDENTIFIED IN TABLE B.3, DDTE/CERTIFICATION SUBCLINS, ARE DELIVERY MILESTONES THAT REPRESENT COMPLETION OF REQUIRED WORK NECESSARY TO ACHIEVE NASA CERTIFICATION. DELIVERY PAYMENT FOR THE ISS DESIGN CERTIFICATION REVIEW (DCR) FOR THE CREWED FLIGHT TO THE ISS INCLUDES ALL WORK UNDER THIS CLIN THAT OCCURS FROM THE CONTRACT EFFECTIVE DATE THROUGH THE ISS DCR COMPLETION. THE DELIVERY PAYMENT FOR THE CERTIFICATION REVIEW (CR) WILL INCLUDE ALL WORK THAT OCCURS FROMTHE ISS DCR DELIVERY DATE THROUGH THE END OF THE DDTE/CERTIFICATION CLIN 001. IN ACCORDANCE WITH CLAUSE C.1, SPECIFICATION/STATEMENT OF WORK, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTING OFFICER MAY ISSUE POST CERTIFICATION MISSION (PCM) TASK ORDERS. THE CONTRACTOR SHALL USE THE MISSION PRICING RATES SHOWN IN TABLE B.4.1, POST CERTIFICATION MISSION PRICES. THE PER MISSION PRICES ARE FOR A SINGLE ORDER AT THE PRICE STATED PER THE CALENDAR YEAR (CY) BASED ON THE NUMBER OF MISSIONS ORDERED. CTS FULL MISSION CAPABILITY PRICES SHALL BE BASED ON (1) FULFILLMENT OF THE DESIGN REFERENCE MISSION TO THE ISS FOUND IN CCT-DRM-1110, CREW TRANSPORTATION SYSTEM DESIGN REFERENCE MISSIONS, ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, AND OTHER TERMS AND CONDITIONS IN THE CONTRACT AND (2) ALL INHERENT CTS CAPABILITIES THAT ARE WITHIN THE PROPOSED MISSION PRICES. IN ACCORDANCE WITH ATTACHMENT J-03, CONTRACT PERFORMANCE WORK STATEMENT, THE TASK ORDERING PROCEDURES AND OTHER TERMS AND CONDITIONS IN THE CONTRACT, THE CONTRACTOR SHALL PERFORM SPECIAL STUDIES, TEST AND ANALYSES, AS INITIATED BY WRITTEN DIRECTION FROM THE CONTRACTING OFFICER
- PIID
- NNK14MA75C
- Award key
- CONT_IDV_NNK14MA75C_8000
- Recipient UEI
- VH1ZJJ9CW9B4
- Source as of
- —
Current award value
—3
Obligated to date
$2,334,729,0942
Potential with options
$4,915,690,3803
- Awarding agency
- National Aeronautics and Space AdministrationNational Aeronautics and Space Administration
- Contractor
- THE BOEING COMPANY
- PSC
- —
- Place of performance
- —
- Set-aside
- No set-aside used
- Pricing
- Firm Fixed Price
- Competition
- Full and Open Competition3 offers received
- Period of performance
- Sep 16, 2014 — Dec 31, 2029
- Benchmark category
- Unclassified
Transaction history
Every action recorded against this award, in the order the government reported them.
| Mod | Action date | Reason | Obligation | Value at action |
|---|---|---|---|---|
| 0 | Sep 16, 2014 | Initial award | $129,300,000.00 | — |
| 1 | Oct 10, 2014 | C | $190,775,675.00 | — |
| 2 | Nov 21, 2014 | B | $0.00 | — |
| 3 | Dec 9, 2014 | C | $119,500,000.00 | — |
| 4 | Dec 15, 2014 | B | $0.00 | — |
| 5 | Jan 8, 2015 | B | $0.00 | — |
| 6 | Jan 21, 2015 | B | $0.00 | — |
| 7 | Jan 30, 2015 | C | $153,284,325.00 | — |
| 8 | May 6, 2015 | B | $59,280,000.00 | — |
| 9 | Jun 8, 2015 | B | $0.00 | — |
| 10 | Jul 14, 2015 | B | $0.00 | — |
| 11 | Jul 28, 2015 | C | $85,260,000.00 | — |
| 12 | Sep 17, 2015 | M | $0.00 | — |
| 13 | Sep 30, 2015 | B | $0.00 | — |
| 14 | Oct 27, 2015 | B | $0.00 | — |
| 15 | Oct 30, 2015 | C | $256,800,000.00 | — |
| 16 | Nov 18, 2015 | C | $0.00 | — |
| 17 | Dec 10, 2015 | B | $0.00 | — |
| 18 | Dec 18, 2015 | B | $0.00 | — |
| 19 | Jan 5, 2016 | B | $0.00 | — |
| 20 | Jan 15, 2016 | B | $0.00 | — |
| 21 | Jan 19, 2016 | C | $72,800,000.00 | — |
| 22 | Feb 24, 2016 | C | $98,800,000.00 | — |
| 23 | Mar 9, 2016 | B | $0.00 | — |
| 24 | Mar 17, 2016 | C | $157,100,000.00 | — |
| 25 | Apr 8, 2016 | B | $0.00 | — |
| 26 | May 13, 2016 | B | $0.00 | — |
| 27 | Jun 6, 2016 | B | $0.00 | — |
| 28 | Jul 28, 2016 | B | $0.00 | — |
| 29 | Sep 1, 2016 | B | $44,753,633.00 | — |
| 30 | Sep 26, 2016 | C | $13,223,924.62 | — |
| 31 | Oct 24, 2016 | B | $0.00 | — |
| 32 | Nov 8, 2016 | C | $46,823,060.38 | — |
| 33 | Dec 8, 2016 | B | $0.00 | — |
| 34 | Dec 16, 2016 | B | $46,297,670.00 | — |
| 35 | Dec 16, 2016 | B | $0.00 | — |
| 36 | Dec 30, 2016 | B | $0.00 | — |
| 37 | Feb 6, 2017 | B | $0.00 | — |
| 38 | Feb 15, 2017 | B | $85,382,452.00 | — |
| 39 | Mar 2, 2017 | B | $0.00 | — |
| 40 | Apr 11, 2017 | B | $0.00 | — |
| 41 | May 10, 2017 | B | $0.00 | — |
| 42 | May 26, 2017 | B | $0.00 | — |
| 43 | Jun 27, 2017 | B | $0.00 | — |
| 44 | Jun 30, 2017 | C | $187,760,985.00 | — |
| 45 | Aug 10, 2017 | B | $0.00 | — |
| 46 | Aug 29, 2017 | B | $0.00 | — |
| 47 | Sep 22, 2017 | C | $59,275,998.00 | — |
| 48 | Oct 4, 2017 | D | $0.00 | — |
| 50 | Oct 23, 2017 | B | $0.00 | — |
| 49 | Oct 24, 2017 | B | $0.00 | — |
| 51 | Nov 28, 2017 | B | $0.00 | — |
| 52 | Dec 18, 2017 | B | $0.00 | — |
| 53 | Feb 1, 2018 | B | $0.00 | — |
| 55 | Mar 1, 2018 | B | $0.00 | — |
| 54 | Mar 16, 2018 | B | $0.00 | — |
| 56 | Mar 23, 2018 | B | $0.00 | — |
| 57 | Mar 30, 2018 | B | $0.00 | — |
| 58 | May 18, 2018 | C | $264,985,413.00 | — |
| 59 | May 22, 2018 | B | $0.00 | — |
| 60 | May 24, 2018 | B | $0.00 | — |
| 61 | Jun 6, 2018 | C | $95,000,000.00 | — |
| 62 | Jun 15, 2018 | B | $0.00 | — |
| 63 | Jun 22, 2018 | B | $0.00 | — |
| 64 | Aug 9, 2018 | B | $0.00 | — |
| 66 | Aug 30, 2018 | D | $0.00 | — |
| 65 | Sep 4, 2018 | C | $1,998,535.00 | — |
| 67 | Sep 19, 2018 | D | $0.00 | — |
| 68 | Sep 28, 2018 | D | $0.00 | — |
| 69 | Oct 5, 2018 | D | $0.00 | — |
| 70 | Nov 1, 2018 | B | $0.00 | — |
| 71 | Nov 2, 2018 | B | $0.00 | — |
| 72 | Nov 2, 2018 | B | $0.00 | — |
| 73 | Nov 9, 2018 | B | $0.00 | — |
| 74 | Nov 9, 2018 | B | $0.00 | — |
| 75 | Dec 4, 2018 | B | $0.00 | — |
| 76 | Dec 5, 2018 | B | $0.00 | — |
| 77 | Dec 14, 2018 | B | $0.00 | — |
| 78 | Jan 22, 2019 | B | $0.00 | — |
| 79 | Feb 6, 2019 | B | $0.00 | — |
| 80 | Feb 7, 2019 | B | $0.00 | — |
| 81 | Feb 14, 2019 | C | $7,610,492.00 | — |
| 82 | Mar 8, 2019 | B | $0.00 | — |
| 83 | Mar 28, 2019 | B | $0.00 | — |
| 84 | Apr 8, 2019 | B | $0.00 | — |
| 85 | Apr 8, 2019 | B | $0.00 | — |
| 86 | May 6, 2019 | B | $0.00 | — |
| 87 | Jun 6, 2019 | B | $0.00 | — |
| 88 | Jun 6, 2019 | B | $0.00 | — |
| 89 | Jun 6, 2019 | B | $0.00 | — |
| 90 | Jun 20, 2019 | B | $0.00 | — |
| 91 | Jun 21, 2019 | B | $0.00 | — |
| 92 | Aug 1, 2019 | B | $0.00 | — |
| 93 | Aug 5, 2019 | B | $0.00 | — |
| 94 | Sep 4, 2019 | B | $0.00 | — |
| 95 | Sep 13, 2019 | B | $0.00 | — |
| 96 | Sep 24, 2019 | C | $14,000,000.00 | — |
| 97 | Sep 30, 2019 | B | $0.00 | — |
| 99 | Nov 1, 2019 | B | $0.00 | — |
| 98 | Nov 7, 2019 | B | $0.00 | — |
| 100 | Nov 8, 2019 | B | $0.00 | — |
| 101 | Dec 18, 2019 | B | $8,000,000.00 | — |
| 102 | Dec 18, 2019 | B | $0.00 | — |
| 103 | Jan 10, 2020 | B | $0.00 | — |
| 104 | Jan 28, 2020 | B | $0.00 | — |
| 105 | Feb 12, 2020 | B | $0.00 | — |
| 106 | Mar 26, 2020 | B | $0.00 | — |
| 108 | Apr 17, 2020 | B | $0.00 | — |
| 109 | May 6, 2020 | B | $0.00 | — |
| 110 | Jul 23, 2020 | B | $0.00 | — |
| 111 | Sep 4, 2020 | B | $0.00 | — |
| 112 | Sep 25, 2020 | C | $1,200,326.00 | — |
| 113 | Oct 26, 2020 | B | $0.00 | — |
| 114 | Oct 26, 2020 | B | $0.00 | — |
| 115 | Dec 3, 2020 | B | $0.00 | — |
| 116 | Dec 18, 2020 | D | $0.00 | — |
| 117 | Jan 14, 2021 | B | $0.00 | — |
| 118 | Jan 27, 2021 | B | $0.00 | — |
| 119 | Feb 4, 2021 | B | $0.00 | — |
| 120 | Apr 27, 2021 | B | $0.00 | — |
| 121 | Jun 2, 2021 | B | $4,728,403.00 | — |
| 122 | Jul 28, 2021 | B | $1,500,000.00 | — |
| 123 | Oct 8, 2021 | B | $311,075.00 | — |
| 124 | Oct 21, 2021 | B | $0.00 | — |
| 126 | Nov 24, 2021 | B | $0.00 | — |
| 127 | Dec 1, 2021 | L | $6,336,745.00 | — |
| 128 | Mar 24, 2022 | B | $10,550,000.00 | — |
| 129 | Apr 18, 2022 | B | $0.00 | — |
| 130 | Jun 6, 2022 | B | $0.00 | — |
| 125 | Jun 24, 2022 | B | $0.00 | — |
| 131 | Jun 30, 2022 | B | $0.00 | — |
| 133 | Aug 22, 2022 | B | $0.00 | — |
| 132 | Aug 23, 2022 | D | $6,300,000.00 | — |
| 134 | Oct 6, 2022 | B | $0.00 | — |
| 135 | Oct 14, 2022 | B | $10,000,000.00 | — |
| 136 | Oct 14, 2022 | B | $0.00 | — |
| 137 | Feb 10, 2023 | B | $0.00 | — |
| 138 | Feb 21, 2023 | B | $0.00 | — |
| 139 | Mar 10, 2023 | B | $0.00 | — |
| 140 | Mar 24, 2023 | L | -$2,150,000.00 | — |
| 141 | Mar 24, 2023 | B | $0.00 | — |
| 142 | Sep 25, 2023 | D | $5,000,000.00 | — |
| 143 | Nov 17, 2023 | B | $0.00 | — |
| 144 | Dec 14, 2023 | B | $0.00 | — |
| 145 | Jan 12, 2024 | B | $0.00 | — |
| 146 | Feb 14, 2024 | B | $0.00 | — |
| 147 | May 7, 2024 | B | $0.00 | — |
| 148 | Jun 28, 2024 | B | $0.00 | — |
| 149 | Jul 29, 2024 | B | $0.00 | — |
| 150 | Oct 17, 2024 | B | $0.00 | — |
| 151 | Jan 27, 2025 | B | $640,000.00 | — |
| 152 | Mar 13, 2025 | B | $0.00 | — |
| 153 | Nov 21, 2025 | B | $0.00 | — |
| 154 | Jan 20, 2026 | B | $0.00 | — |
| 156 | Jun 25, 2026 | B | $0.00 | — |
| 155 | Jul 8, 2026 | B | $0.00 | — |
| 157 | Jul 9, 2026 | B | $0.00 | — |
| 158 | Sep 28, 2026 | B | $92,300,382.00 | — |
| 159 | Oct 13, 2026 | B | $0.00 | — |
Provenance
Which source record produced each displayed rollup figure.
| Field | Source | File | Retrieved | Parser | Artifact hash |
|---|---|---|---|---|---|
| awarding_agency_id | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| contractor_id | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| current_award_value | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| naics_code | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| potential_award_value | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| psc_code | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
| total_obligated | USAspending.gov | — | Oct 16, 2026 | usaspending_contract_csv@2026.08.2 | acc02768946d |
Sources and method
Figures on this page are computed from public federal award records. Numbers are never estimated or generated; where a figure is withheld, the reason is stated rather than filled in.
This page is a record of one federal award, assembled from the transactions the government published against it. Note 1 describes where the rollup came from. Values are award values, not unit prices.
- 1Rollup values derive from 159 transaction records parsed from USAspending.gov, retrieved Oct 16, 2026 by transform awards@2026.08.1.
- 2Obligations are the sum of signed federal action obligations across all transactions; deobligations are negative and remain negative.
- 3Current and potential award values are taken from the latest reported action, not summed across modifications.